PUBLIC HEALTH AND MUNICIPAL ENGINEERING DEPARTMENT | ||
BRIEF NOTE ON KHAMMAM WATER SUPPLY IMPROVEMENT SCHEME UNDER | ||
UIDSSMT (SUB PLAN OF JNNURM) | ||
1 | Administrative Sanction | G.O.Rt.No.1178 , Dt.17-09-2011, for Rs.7410 Lakhs |
2 | Technical Sanction | ENC(PH) R.No:76/2011-12 ,Dt:23-11-2011, for Rs.5070.90 Lakhs Civil Works & 2330.10 Lakhs for O&M for 7 years (including 2 Yers Defect liability period) |
3 | Foundation Stone Laid | By Hon’ble Chief Minister on 24-11-2011. |
4 | Tender Approval | G.O.Rt.No: 97 , Dt: 23-01-2012 |
5 | Name of the Agency | Sri. Velagapudi Rama Rao |
6 | Agreement No | SE CR (PH) Wgl No.12/2011-12, Dt:02-02-2012. |
7 | Agreed period of Completion | 24 Months. |
MAIN COMPONENTG OF SCHEME | STAGE OF WORK | |
1 | Raising & Strengthening of Weir across Munneru River | The CE CDO recommended for construction of new weir instead of raising the height of existing weir.Hence the revised estimate has forwarded to ENC(PH) ,Hyderabad. |
2 | 8.0 m dia Intake Well cum Pump House | Pump House Roof Slab Completed(95%) |
3 | 16.5 MLD Rapid Gravity Filtration Plant at Danavaigudem Head Works | Roof Slab completed(80%) |
4 | 700 KL Clear Water Sump at Danavaigudem Head Works | PCC for Foundation Completed(35%) |
5 | Clear Water Pump House at Danavaigudem Head Works | Yet to be started (dependent work of Sump) |
6 | 1200 KL capacity ELBR at Ramanagutta | Completed up to 1st Brace level(35%) |
7 | 600 KL capacity ELBR at Raganayakulagutta | Bottom Dome completed& side wall is in progress(88%) |
8 | 600 KL Capacity ELSR at NSP Camp | up to 4th Brace completed(50%) |
9 | 500 KL Capacity ELSR at Khilla | up to 4th Brace completed(50%) |
10 | 500 KL Capacity ELSR at Pakabanda Bazar | up to 4th Brace completed(50%) |
11 | 1000 KL Capacity ELSR at Parikamukkala Colony | 1st Brace Completed (40%) |
12 | 1200 KL capacity ELSR at Teachers Colony | Top Dome completed(95%) |
13 | 250 KL Clear Water Sump at Ranganayakula Gutta | Yet to be started |
14 | Raw Water & Clear Water Pumpsets | Pumpsets Supplied |
15 | Pumping Mains & Gravity Mains | 6.20 km laid against 12.34 kms. |
17 | Distribution Lines | 43.50 km laid against 57.67 Kms |
18 | Staff Quartes & Compound Walls | Yet to be started |
TOTAL AMOUNT OF WORK DONE (up to 07-11-2013) is 27.96 Crores(65 %) against 43.07 Crores |